Methodology / Lead time
Lead time — definition and counting
Time from order and drawing confirmation to dispatch, queueing included, excluding customer-side delays.
- Unit
- days
- Formula
- scheduling queue + material preparation + machining + surface finishing (outsourced) + inspection + packaging
Why suppliers disagree
- Sample versus batch: seven days and 45 days are both normal and cannot be quoted as one number
- Whether queueing is included; when capacity is full, queueing can be half the lead time
- Outsourced steps: anodising and heat treatment are frequent bottlenecks the plant does not control
- Inspection: full inspection versus sampling differs by days
- Holidays: the month around Chinese New Year is effectively lost capacity
How to collect it on site
- Ask how many days the last comparable batch actually took, not how long it usually takes
- Ask for three months of order-to-dispatch records
- Ask which subcontractor handles finishing and what their lead time is
- Record promised lead time and actual lead time separately
The three most common misreadings
- Quoting stock-item lead time for a custom part
- Ignoring subcontractor queues; finishing shops can add two weeks in peak season
- Treating 'scheduled' as 'started'
How to use this page: align the basis before you compare. Give the same drawing and the same quantity to three suppliers, ask each to fill in these items, and only then are the totals comparable.