Methodology / Monthly capacity
Monthly capacity — definition and counting
Conforming units deliverable within one month. It is not the theoretical output of the equipment.
- Unit
- units / month
- Formula
- machines x cycle time per unit x effective hours x yield x utilisation
Why suppliers disagree
- Shifts: one shift of eight hours, two shifts or three shifts triples the same equipment
- Blank or finished part: whether upstream casting and downstream heat treatment are included
- Outsourced steps: many plants count subcontractor capacity as their own
- Which yield: trial yield, volume yield, or the best month
- Utilisation assumption: 85% and 60% are different businesses
- Planned versus commissioned capacity: 'at full ramp' in a placement document is not today
How to collect it on site
- Count nameplates and machines on site; do not rely on what you are told
- Read actual cycle time from the process card, not theoretical time from the routing document
- Ask for the outsourcing share and the name of the subcontractor
- Ask for the last three months of shipping records and divide units by months
- Ask for planned, under construction and commissioned as three separate answers
The three most common misreadings
- Treating design capacity as actual capacity, which is routinely 30% higher
- Treating a peak month as an average month; peak-season data has no reference value
- Ignoring changeover time, which can consume half the capacity in high-mix low-volume work
- Taking 'planned capacity' in a listed-company announcement as current capacity
How to use this page: align the basis before you compare. Give the same drawing and the same quantity to three suppliers, ask each to fill in these items, and only then are the totals comparable.